Civil works during pipeline construction projects
| Location | Cherouq concession; Oued ZarConcession,… |
| Year | 2009-2014 |
| Client | OMV Tunisia; ENI Tunisia |
| Project Description | Roads construction during pipeline construction mainly • right of way opening with 20m widths • earthmoving works (11 ha during gas valorization pipeline project; 15 ha during Karma Gas Lift project) prior pipelines trench excavation. • Tuff installation and compaction • Anchor blocs construction; • Concrete foundations construction |