6” HDPE fire water system for the gas lift plant at Waha CPF

Location Cherouq concession
Year 2011
Client OMV
Project Description Engineering, procurement, construction and testing of of 6” HDPE Buried Fire Water System for the Gas Lift Plant at Waha CPF:
• Line Diameter : 6”, 4” & 2”
• Pipe Schedule: PN20
• Material : HDPE
• Pipeline Length : 0,5Km